Analisa Perbandingan Penggunaan Bekisting Konvensional dengan Pra Cetak pada Pekerjaan Kolom Apartemen Begawan Malang

  • Paskalis Aek Program Studi Teknik Kimia Fakultas Teknik, Universitas Tribhuwana Tunggadewi Malang https://orcid.org/0000-0002-5646-0722
  • Suhudi Program Studi Teknik Sipil, Fakultas Teknik, Universitas Trihuwana Tunggadewi Malang
  • Handika Setya Wijaya Program Studi Teknik Sipil, Fakultas Teknik, Universitas Trihuwana Tunggadewi Malang
Keywords: Pre-cast Formwork; Conventional; cost and time

Abstract

Technology in the world of construction is growing rapidly marked by the emergence of various new innovations, both in terms of equipment, materials, and methods of implementation. One of the construction work that has new innovations is formwork work. At present various kinds of materials with better quality have started to be used for construction work, especially for formwork material for high rise building project work. This requires an analysis of the type of formwork material that will be used. The results of the analysis of the calculation of the cost of formwork for column work in the construction of Begawan Apartment Malang Area GWT (Ground Water Tank) using pre-cast formwork is cheaper or 4% smaller than the use of conventional formwork material. For the total cost of column formwork using pre-printed Rp. 5.687.529,50, using conventional formwork in the amount of Rp.27.316.805,67 and the difference in both of them in the amount of Rp.22.629.276,17. From the analysis of observations of conventional and preprinted formwork time, it can be seen that conventional formwork time has 18 days while conventional formwork work has 12 days.

Author Biography

Paskalis Aek, Program Studi Teknik Kimia Fakultas Teknik, Universitas Tribhuwana Tunggadewi Malang

 

 

References

Baharudin dan Dodi, 2008. Studi Perbandingan Penggunaan Bekisting Tradisonal dengan Bekisting Prafabrikasi Sebagai Cetakan Beton Pada Proyek Konstruksi Gedung Bertingkat, Institut Teknologi Bandung

American Concrete Institute, 1990. ACI 318-89 Formwork for Concrete, Part I, Fitth Edition, Skokie, Illinois, USA, PCA.

Hanna Awad S, 1999. Concrete Formwork System, Marcel Dekker, University of Wisconsin, New York.

Stephens, 1985. Pengertian Bekisting, http:/e-journal.uajy.ac.id. Diakses tanggal 18 Januari 2018.

Clarasinta, E. ( 2012 ).Tugas Akhir : Analisa biaya dan waktu dan bekisting metode semi sistem (besi hollow) dengan konvensional pada proyek Puncak Kertajaya Apartement. Surabaya : Institut Teknologi Sepuluh Nopember

Wigbout, F.Ing. 1992. Pedoman Tentang Bekisting (Kotak Cetak). Erlangga. Jakarta

Published
2019-10-25