Analisa Perbandingan Biaya Material Pasangan Bata Merah, Bata Ringan dan Batako pada Proyek Pembangunan Museum MPU Purwa Malang

  • Fransiska Romana Asuat Program Studi Teknik Sipil, Fakultas Teknik, Universitas Tribhuwana Tunggadewi Malang
  • Andy Kristafi Arifianto Program Studi Teknik Sipil, Fakultas Teknik, Universitas Tribhuwana Tunggadewi Malang
  • Handika Setya Wijaya Program Studi Teknik Sipil, Fakultas Teknik, Universitas Tribhuwana Tunggadewi Malang
Keywords: brick pair, comparison of cost, time schedule

Abstract

Wall is a building element that functions to separate and form space. As technology advances, many choices of materials are used to save the cost and time of wall installation work. Productivity enhancement activities are an effort to improve the value of productivity that has been planned, wherein this activity requires field data. Labor and high volume of work will certainly require high costs so that a good level of productivity will minimize project costs and optimal work time. The object of the research is MPU Purwa Building, Malang City with an average brick wall area of ​​107.48 m2 and the second floor masonry wall area is 58.47 m2. The working group determined as many as 3 groups according to the type of masonry used and with each combination was group 1 with 1 worker 2 workers, group 2 with 1 worker 2 workers, and group 3 with 1 worker 2 workers and group 4 with 1 worker 2 workers. Research observations were carried out with a total of 3 days of observation. Research analysis is carried out on the productivity and efficiency of each working group. The most optimal working group in terms of cost is work group 3 with a combination of 1 worker and 2 workers. This working group has a cost of Rp 88,186,456.01. Whereas the most optimal working group in terms of time is working group 2 with a combination of 1 worker and 2 workers. This working group has a work completion time of 1 m2 for 5 working days compared to other work groups.

 

References

[1] Tarore, D. I. (2010). Manajemen Konstruksi. Jakarta: Gapeksindo.
[2] Sahid, M.N dan Soharto I. 2010. Analisa Perbandingan Produktivitas Kerja Pada Pekerjaan Bata Konvensional dengan Dinding Balok Hebel. Simposium Nasional. Universitas Muhammadiyah Surakarta.
[3] Susanta, Gatut. 2008. Panduan Lengkap Membangun Rumah. Depok: Penerbit Swadaya.
[4] Jayabata, Doedi.2014. Memilih antara Bata Merah atau Batako, akses online 12 Juni 2018. URL : http://doedijayabata.blogspot.com/2014/01/memilih-antara-bata-merahbatakoatau.html
[5] Badan Standarisasi Nasional. 2008. Standar Nasional Indonesia (SNI). SNI. 4869.1-2008. Semen Beku Sapi. Jakarta.
Published
2019-07-24